Skip to content

Lead Time: How to Measure It and Why It Matters

Blog Restocked 4 min read

Lead time is the time between placing an order with a supplier and having the stock ready to sell. It is one of the two biggest inputs to your reorder point, along with daily sales, and it is often guessed rather than measured.

Measure the full lead time

Lead time isn’t just shipping. It includes:

  • Time for the supplier to confirm and pick the order.
  • Transit time.
  • Time for you to receive, check and shelve the stock.

If the supplier quotes 7 days but it takes you 2 days to receive and shelve, your lead time is 9 days.

An example lead-time log

PO Sent Available to sell Days
1041 3 Mar 13 Mar 10
1056 24 Mar 5 Apr 12
1073 15 Apr 23 Apr 8
1090 6 May 20 May 14

The average is 11 days and the longest recent delivery was 14. Planning on the supplier’s quoted 7 days would leave you short on every order. Using 11 days for the reorder point, with safety stock that covers the spread, keeps you in stock.

How long four orders really took (days)PO 104110 daysPO 105612 daysPO 10738 daysPO 109014 daysQuoted: 7Average: 11
The supplier quotes 7 days, but the real average is 11 and the longest was 14.

Include your own receiving time

The clock stops when the stock is on the shelf and sellable in Shopify, not when the van arrives. If deliveries sit unopened for two days because the team is busy, that is part of your lead time too. Receiving promptly against the purchase order shortens lead time for free.

Lead time and cash

Every day of lead time is stock you have to hold or have in transit. A shorter, more reliable supplier can be worth a slightly higher unit price because you hold less stock and run out less. When comparing suppliers, compare the total: unit cost plus the cash tied up in the extra stock a long lead time requires.

Ways to shorten lead time

  • Order on a fixed day each week, so suppliers can plan picking.
  • Send POs early in the day, before the supplier’s cut-off.
  • Receive deliveries the same day they arrive.
  • Ask about local stock, regional warehouses or faster shipping on key products.

Seasonal changes

Lead times often stretch before holidays and around factory shutdowns, such as Lunar New Year for many overseas suppliers. Add the expected delay to your lead time a few weeks ahead, and order earlier. Our guide to safety stock shows how variable lead times change the buffer you need.

Talk to suppliers about lead time

Suppliers rarely volunteer that they are running late. A few habits keep you informed:

  • Ask for a confirmed ship date with every PO, not just “in stock”.
  • Ask for tracking or a shipping notice when the order leaves.
  • Share your measured lead times with the supplier. Showing them that deliveries have averaged 11 days against a quoted 7 often prompts a better answer, or a more honest quote.

Keep a note of any supplier who is consistently late, and factor it into your choice of supplier, not just your safety stock. A cheaper unit price from an unreliable supplier can cost more in stockouts and extra stock than it saves. For how lead time feeds your ordering, see how to calculate a reorder point.

How to track it

  1. Record the date you send each purchase order.
  2. Record the date the stock is received and available to sell.
  3. Keep a running average per supplier, and note the longest recent delivery.

Why variability matters

A supplier who always takes 14 days is easier to plan for than one who takes anywhere from 7 to 21. Variable lead times need more safety stock, because you have to cover the slow deliveries too.

What lead time does to your numbers

For a product selling 5 a day, each extra day of lead time adds 5 units to the reorder point, plus extra safety stock. Moving from a 10-day to a 30-day supplier triples the stock you need in the pipeline.

When lead times change

Update them before peak season and after any supplier change. A stale lead time is one of the most common reasons reorder points stop working.

How Restocked helps

Restocked uses per-SKU lead times in every reorder point and safety stock calculation, and shows lead time as part of the math behind each recommendation. Need the basics? See the inventory glossary.

Read next: Stocky Alternatives Compared: Purchase Order Apps for Shopify · How Stockouts Distort Your Demand Forecast

FAQ

Should I use the quoted or the actual lead time?

The actual one, measured from your own orders. Quoted lead times are usually optimistic.

How many orders do I need to measure lead time?

Even three or four orders give a better estimate than the quote. Keep updating it as more orders arrive.